Current Projects

Council simultaneously undertakes many projects throughout the municipality. Below is a snapshot of what we're currently working on. The full Capital Works Program can be found in our latest budget.


Road Reconstruction
The tender for the reconstruction of Pitt Avenue, Trevallyn was accepted at the March 2021 Council Meeting. The Baker Group will commence work on Monday 28th June 2021. Further information about the project can be found in the Latest News section of our website.


Bridge Strengthening
Bridge 2634 on Winkleigh Road, Winkleigh will be strengthened by BridgePro as their tender was accepted at our January 2021 Council Meeting. Works are scheduled to be undertaken in October 2021.


New Kerb and Footpath
A new kerb and footpath will be constructed on Gravelly Beach Road, Gravelly Beach from Monday 4th October for approximately 4 weeks.


New Kerb and Footpath
A new kerb and footpath will be constructed on Rosevears Drive, Lanena. This will connect the footpath constructed by the Department of State Growth in their recent upgrades to the West Tamar Highway, with the footpath which we've been constructing south along Rosevears Drive. Works will begin on Monday 4th October and run for approximately 4 weeks.


New Kerb and Stormwater Infrastructure
We will be constructing a new kerb from the Cul-de-sac to the existing kerb on Paringa Ave, Lanena. The new works include stormwater, pavement and open drain construction. Work will begin on Monday 11th October and take approximately 6 weeks.


Starting Soon:

Repairs and Resurfacing
Localised repairs and resurfacing will occur on Deviot Road, Deviot between Paper Beach Road and Motor Road. Work will be undertaken in two stages with some asphalting occurring in 2021, prior to resurfacing in 2022. The contract was awarded to Harding Hotmix at our August 2021 Council Meeting.


Road Reconstruction
Long Plains Road, Bridgenorth will be reconstructed in Stage 2 of works. The contract was awarded to Walters Contracting at our August 2021 Council Meeting.


Recently Completed:

New Footpath
A new footpath is being constructed in Jellico Street, Beauty Point between Mainwaring and Charles Streets. Works are expected to take between 5-6 weeks, weather permitting.


Road Widening and Drainage Improvements
The Tender for road widening and drainage improvements on Flinders Street, Beauty Point was awarded at the March 2021 Council Meeting. Andrew Walters Construction began work in May and completed it in September 2021.


Footpath Extension
The footpath on Rosevears Drive, Lanena has been extended as part of our second Stimulus Package. The tender was awarded to The Baker Group who widened the road, provided kerb & channel as required and installed a new footpath between number 48 and 86.

Scroll Top