Current Projects

Council simultaneously undertakes many projects throughout the municipality. Below is a snapshot of what we're currently working on. The full Capital Works Program can be found in our latest budget.


Road Reconstruction
The tender for the reconstruction of Pitt Avenue, Trevallyn was accepted at the March 2021 Council Meeting. The Baker Group will commence work on Monday 28th June 2021. Further information about the project can be found in the Latest News section of our website.


Road Widening and Drainage Improvements
The Tender for road widening and drainage improvements on Flinders Street, Beauty Point was awarded at the March 2021 Council Meeting. Andrew Walters Construction began work in May and expect it will take approximately 16 weeks to complete.


Guardrail Installation
Bridge 2634 on Winkleigh Road, Winkleigh will have a guardrail installed by BridgePro from Monday 28th June 2021. One lane of traffic will be open at all times. Some delays may occur.


New Footpath
A new footpath is being constructed in Jellico Street, Beauty Point between Mainwaring and Charles Streets. Works are expected to take between 5-6 weeks, weather permitting.


Starting Soon:

 

Bridge Strengthening
Bridge 2634 on Winkleigh Road, Winkleigh will be strengthened by BridgePro as their tender was accepted at our January 2021 Council Meeting. Works are likely to occur in October 2021.


New Kerb and Footpath
A new kerb and footpath will be constructed on Gravelly Beach Road, Gravelly Beach.


Recently Completed:

Footpath Extension
The footpath on Rosevears Drive, Lanena has been extended as part of our second Stimulus Package. The tender was awarded to The Baker Group who widened the road, provided kerb & channel as required and installed a new footpath between number 48 and 86.

Sculpture Installation
'Pledged' has been installed on the headland at Gravelly Beach as part of the Gravelly Beach Foreshore Master Plan. This sculpture was the most recent winner of the Artentwine Sculpture Biennial by Wayne Z Hudson.

Road Reconstruction
Our Contractor, R J May Civil Construction, has recently reconstructed the road and upgraded the stormwater system, as well as installing a new kerb on Loongana Street, Gravelly Beach.
This was completed thanks to the Federal Government's Local Roads and Community Infrastructure Program Phase 2.


Shoulder Widening and New Kerb
Our Contractor, R J May Civil Construction, has recently widened the shoulders and installed a new kerb and associated drainage works on Nairana Street between Taroona Street and Teggs Road, Gravelly Beach.
This was completed as part of our Second Stimulus Package 2020/2021, thanks to the Federal Government's Local Roads and Community Infrastructure Program.

Scroll Top